What it costs in government fees to build a home in Weld County, Colorado

Every impact fee, water and sewer connection charge, and building permit for a new single-family detached home in unincorporated Weld County — itemized, sourced, and dated.

11 fees verified 19 source documents Compiled Jul 31, 2026

Your project

Total government fees $30,158 Single-family detached, 2,000 sq ft finished, 4BR, on a platted lot in the unincorporated county — water and sewer from whichever special district serves the parcel. Ranges from $12,658 (a lot on private well and septic, the dominant pattern in central and eastern Weld) to $135,958 (a lot classed 5/8 inch Standard by Little Thompson, paying full cash-in-lieu of water rights, plus septic).
What this specific number is. Little Thompson Water District tap in a platted subdivision where the developer already dedicated water rights and installed the meter pit, plus septic. It is one point inside a 10.7× range — $12,658 to $135,958 for the identical house on different lots in the same county. This range is the same house on DIFFERENT LOTS, not the same lot priced two ways. Three things change across it: whether the parcel has district water at all, which tap class the district assigns the lot, and whether the developer already dedicated raw water rights. Holding the lot fixed, only the third applies — and that alone is a 3.1x swing on the tap. In Colorado the question "what does it cost here" has no single answer until you name the parcel and its service district, so read the range as the real answer and the headline as one worked example.
Check the utility provider before you rely on thisWater is the single largest variable here and it is never the county. Three independent rural water districts serve unincorporated Weld. The modeled case is a Little Thompson Inside Use Single Family tap where the developer already dedicated raw water rights and installed the meter pit: $17,600, or 63% of the stack. Holding that same tap class and removing only the developer dedication takes it to $54,650 — a 3.1x swing on one footnote in the plat. The county's full range is far wider than that, but only because tap class itself changes with the lot.
Impact & mobility fees
FeeAmount
Road Impact Fee — all new single family dwellings Eff. Jan 1, 2026 · Ch. 20 · source Rose from $3,567 in 2025. $3,794.00
County Facilities Impact Fee — all new single family dwellings Eff. Jan 1, 2026 · Ch. 20 · source $1,636.00
Drainage Fee Eff. Jan 1, 2026 · Ch. 20 · source ⚠ $0.22 per impervious square foot, and impervious area INCLUDES the adjacent street right-of-way up to the centerline. That makes it parcel-specific — the working band is $528 to $1,300. $748.00
Subtotal$6,178
Water & sewer — Little Thompson Water District
FeeAmount
Plant Investment Fee — Little Thompson, inside-use single family Eff. Apr 17, 2026 · source ⚠ Cash-in-lieu of water rights is $33,750 to $148,500 depending on tap class and is $0 only if the developer already dedicated. Cash-in-lieu is priced at $135,000 per acre-foot. $15,900.00
Residential OWTS permit — new (septic) Eff. Feb 26, 2025 · source Septic is the realistic wastewater default across most of unincorporated Weld. $1,500.00
Water Resource fee — Little Thompson Eff. Apr 17, 2026 · source $1,000.00
Installation — developer already installed service line and meter pit Eff. Apr 17, 2026 · source $4,000 if the developer did not. $700.00
Subtotal$19,100
Building permits, surcharges & other
FeeAmount
Building Permit Fee Eff. Jan 1, 2026 · source ⚠ Valuation from a nine-column table by construction class. R-3 spans $215.90 (Type IA) to $169.09 (Type VB). Reading the leftmost column overstates valuation by 28%. Wood frame is Type VB. Garage, basement and deck price separately and additively. $2,700.00
Major Plan Review — new single family dwelling Eff. Jan 1, 2026 · source 70% of the building fee — was 65% in 2025. $1,890.00
Access permit — residential Eff. Jan 1, 2026 · source $200.00
Electrical permit — residential, 1,501 to 2,000 sq ft Eff. Jan 1, 2026 · source Based on enclosed living area. Weld issues its own electrical permits rather than deferring to the State Electrical Board. $90.00
Subtotal$4,880

Water provider

Tap class is driven by lot size and use class, NOT nominal meter diameter. A spec sheet saying '3/4 inch meter' maps to the wrong row in two of these three districts.

DistrictFee
Private well and septic$1,600
Little Thompson, developer dedicated water$17,600
North Weld County 50% tap$62,690
North Weld County full standard tap$99,440
Little Thompson 5/8 inch Standard, full cash-in-lieu$123,400

Fees Weld County does not charge

Verified absent, so you don't go looking for them.

What we could not verify These are reported as gaps rather than estimated. The total above is a floor.

Why this number is easy to get wrong

This page models one house. 2,000 sq ft, single-family detached, Private well and septic. If you're underwriting an actual project — a unit mix, a different district, a CO date that might slip past a scheduled increase — we compute that stack for you.
Need a county we haven't published? That's the main thing we do.
from $290 What we compile, and what it costs →
How to use this. Every figure is transcribed from an official Weld County, service-district or Colorado Revised Statutes document, linked inline, with its effective date. No third-party legal-code mirrors were used — in testing, one returned impact fees off by 2.4×. Water and sewer is 63% of this stack. Built for screening and pro-forma work; confirm with the county and the district before you sign anything.